Idaho H 895: DATA CENTERS – Adds to existing law to establish limitations on consumptive use of water for cooling certain data centers

Status
Enacted
Enacted
In effect since
Last action

What it does

Prohibits data centers beginning construction after 1 July 2026 from using water for cooling unless supplied by municipal or water district systems.

What it requires

Data centers that begin construction on or after July 1, 2026, may not use water for cooling purposes as a consumptive use unless the water is supplied by a municipal, water district, or water and sewer district water system. The director of the Department of Water Resources must consider legislative findings regarding data center consumptive use and its impacts when evaluating new appropriations or transfers of water rights for data centers.

Drafted by software from the bill text and not reviewed by an attorney. Check the official text before relying on it.

Email me when new Idaho data centers and energy laws pass or take effect

Free. At most one email a week, only when a law is signed or takes effect. Unsubscribe in one click.

History

  1. Reported Signed by Governor on April 2, 2026 Session Law Chapter 291 Effective: 07/01/2026

  2. Delivered to Governor at 4:12 p.m. on April 1, 2026

  3. Returned Signed by the President; Ordered Transmitted to Governor

  4. Signed by President; returned to House

  5. Received from the House enrolled/signed by Speaker

  6. Reported Enrolled; Signed by Speaker; Transmitted to Senate

  7. Returned from Senate Passed; to JRA for Enrolling

  8. Read third time in full – PASSED - 32-1-2AYES – Adams, Bernt, Bjerke(Bjerke), Blaylock, Burtenshaw, Carlson, Cook, Den Hartog, Foreman, Grow, Guthrie, Harris, Hart, Keyser, Kohl, Lakey, Lenney, Lent, Nichols, Okuniewicz, Rabe, Ricks, Ruchti, Semmelroth, Shippy, Taylor, Toews, VanOrden, Ward-Engelking, Woodward, Zito, ZuiderveldNAYS – GallowayAbsent and excused – Anthon, WintrowFloor Sponsor - BurtenshawTitle apvd - to House

  9. Read second time; filed for Third Reading

  10. Reported out of Committee with Do Pass Recommendation; Filed for second reading

  11. Introduced, read first time; referred to: Resources & Environment

  12. Received from the House passed; filed for first reading

  13. Rules Suspended: Ayes 70 Nays 0 Abs/Excd 0, read in full as required – PASSED - 58-10-2AYES – Barbieri, Berch, Bingham, Boyle, Bruce, Burgoyne, Cannon, Cheatum, Church, Cornilles, Crane(12), Crane(13), Dygert, Egbert, Ehardt, Ehlers, Erickson, Fuhriman, Furniss, Galaviz, Gannon, Garner, Green, Hall(Stone), Handy, Haws, Healey, Holtzclaw, Hostetler, Leavitt, Manwaring, Marmon, Mathias, McCann, Mendive, Mickelsen, Miller, Mitchell, Monks, Nelsen, Palmer, Petzke, Pickett, Pohanka, Raybould, Raymond, Redman, Rubel, Sauter, Shepherd, Shirts, Tanner(14), Thompson, Vander Woude, Veile, Weber, Wheeler, Mr. SpeakerNAYS – Beiswenger, Cayler, Harris, Hawkins, Price, Rasor, Scott, Skaug, Tanner(13), WisniewskiAbsent – Alfieri, HillFloor Sponsor - RaybouldTitle apvd - to Senate

  14. Read second time; Filed for Third Reading

  15. Reported out of Committee with Do Pass Recommendation, Filed for Second Reading

Know the next Idaho data centers and energy law while it is a bill