Adds Section 61-335 to Idaho Code requiring public utilities to procure electric service for new large loads (30+ megawatts increase within 12 months) from sources outside existing resources, prohibiting cost recovery from other ratepayers, and allowing customers to competitively procure such service with utility transmission and distribution access at cost.

Drafted by software from the bill text and not reviewed by an attorney. Check the official text before relying on it.

Email me when new Idaho data centers and energy laws pass or take effect

Free. At most one email a week, only when a law is signed or takes effect. Unsubscribe in one click.

History

  1. Introduced, read first time; referred to: State Affairs

  2. Received from the House passed; filed for first reading

  3. Rules Suspended: Ayes 70 Nays 0 Abs/Excd 0, read in full as required – PASSED - 62-8-0AYES – Alfieri, Andrus, Barbieri, Beiswenger, Berch, Boyle, Bruce, Burgoyne, Cannon, Cayler, Cheatum, Clow, Cornilles, Crane(12), Crane(13), Dygert, Ehardt, Ehlers, Erickson, Fuhriman, Furniss, Gannon, Garner, Handy, Harris, Hawkins, Healey, Hill, Holtzclaw, Horman, Hostetler, Leavitt, Manwaring, McCann, Mendive, Mickelsen, Miller, Mitchell, Monks, Nelsen, Palmer, Petzke, Pickett, Pohanka, Price, Rasor, Raybould, Raymond, Redman, Sauter, Scott, Shepherd, Shirts, Skaug, Tanner(13), Tanner(14), Thompson, Vander Woude, Weber, Wheeler, Wisniewski, Mr. SpeakerNAYS – Achilles, Church, Egbert, Galaviz, Green(Lesmeister), Marmon, Mathias, RubelAbsent – NoneFloor Sponsor - GarnerTitle apvd - to Senate

  4. Read second time as amended; Filed for Third Reading

  5. Read first time as amended; filed for Second Reading

  6. Reported Engrossed; Filed for First Reading of Engrossed Bills

  7. Bill as Amended Referred to JRA for Engrossing

  8. Amendments Referred to the JRA for Printing

  9. Reported out without recommendation as amended

  10. Referred to the Committee of the Whole

  11. U.C. to be placed on General Orders, no objection

  12. U.C. to hold place on third reading calendar one legislative day

  13. U.C. to hold place on third reading calendar one legislative day

  14. U.C. to hold place on third reading calendar one legislative day

  15. U.C. to hold place on third reading calendar one legislative day