Large-load tariffs and cost allocation laws by state
177 bills on large-load tariffs and cost allocation in 44 jurisdictions, 27 of them enacted in 2025 and 2026. The laws come first, with what each requires, then the bills that moved most recently.
- 27 laws enacted in 2025 and 2026, in 18 states. Most: California (4), Delaware (4), Nebraska (2).
- 177 bills in 44 jurisdictions, 9 of them in Congress. Latest action 9 November 2026.
Updated 16 November 2026LawsRecent billsBy state
Enacted in 2025 and 2026
27 laws, by state. Laws enacted before 2025 are not listed.
Alabama
Enacted
SB 270: Electric Utilities; review by Public Service Commission of certain contracts with large load data centers further provided for
The Public Service Commission must review and approve retail electric service contracts between utilities and large load data center customers. The Commission must determine that such contracts provide for recovery of incremental costs and promote positive benefits to other retail electric customers of the utility.
Took effect 1 October 2026
Arizona
Enacted
HB 2756: utilities; high load factor customers
Electric public service corporations and public power entities serving more than one million connections must file quarterly reports with the Corporation Commission or governing body regarding new extra high load factor customers, including numbers of interconnection requests and completed interconnections. Electric public service corporations must file cost-of-service studies within 180 days. Entities conducting integrated planning must include extra high load factor customers in load growth projections.
California
Enacted
AB 2383: Electricity: data centers.
Each electrical corporation must file transmission and distribution service and generation service tariffs for participating data centers. Each community choice aggregator or electric service provider must adopt a generation service tariff for data centers by January 1, 2028. All tariffs must allocate incremental costs to data centers and prevent cost shifts to other ratepayers.
Takes effect 1 January 2027
Enacted
SB 1168: Data centers: rate structures.
The Public Utilities Commission must assess opportunities for rate structures in new or existing proceedings to ensure data centers pay their reasonable share of transmission and distribution costs, pay their proportionate share of load increases and procurements needed to reliably serve their loads, and alleviate cost pressures on residential ratepayers.
Takes effect 1 January 2027
Enacted
SB 886: California Technology Innovation and Ratepayer Protection Act.
The Public Utilities Commission must establish new tariffs or update existing electric rules by January 1, 2028 for interconnection of participating customer facilities and provision of retail electric service to participating customers. The commission must evaluate risks and benefits to nonparticipating customers, prevent stranded costs or cost shifts to them, and ensure generation charges for unbundled customers appear as separate line items.
Takes effect 1 January 2027
Enacted
SB 57: Electrical corporations: data centers: report.
The Public Utilities Commission may assess whether electrical corporation costs associated with new loads from data centers result in cost shifts to other customers. The commission must submit this assessment to relevant legislative policy committees and publicly post it on the commission's website on or before January 1, 2027.
Delaware
Enacted
HB 233: An act to amend title 26 of the delaware code relating to large energy use facilities.
Commission-regulated electric utilities must establish a separate rate class for large energy use facilities and require them to obtain Commission approval of an Electric Service Agreement and Transmission Service Agreement before beginning operations. Large energy use facilities must pay minimum 90% of contract capacity for distribution and supply costs, maintain curtailment capability, provide financial security, and contribute to low-income and green energy funds.
Enacted
HB 310: An act to amend title 30 of the delaware code relating to business tax credits and deductions.
Amends the definition of 'qualified facility' in Delaware tax code to exclude large energy use facilities (those using 30 megawatts or more and primarily providing data center services) from eligibility for business tax credits and license fee reductions.
Enacted
SB 308: An act to amend title 26 of the delaware code relating to the load forecast accountability act.
Amends the Load Forecast Accountability Act to require the Delaware Public Service Commission to consider four specific factors when investigating electric distribution companies' load forecast methodologies: project development status, ramping schedules, duplicative interconnection requests, and customer financial commitments.
Enacted
SB 276: An act to amend title 26 of the delaware code relating to electric utilities.
Electric cooperatives that have implemented a restructuring plan providing retail competition must provide electric supply service to all customers in their service territory with projected monthly demand of 50MW or less. Electric cooperatives have the right but not the obligation to provide service to customers with projected monthly demand exceeding 50MW.
Florida
Enacted
SB 484: Data Centers
Public utilities must file tariffs by October 1, 2026 ensuring large load customers bear their full cost of service without shifting costs to other ratepayers. Public utilities may not knowingly provide electric service to foreign entities qualifying as large load customers. Water management districts and the Department of Environmental Protection must require reclaimed water use by large-scale data centers when feasible.
Took effect 1 July 2026
Idaho
Enacted
H 911: PUBLIC UTILITIES – Adds to existing law to provide for new large loads.
Public utilities must obtain commission approval before providing service to new large loads. Service contracts must include a no harm test demonstrating the load maintains service quality and funds its full cost of service. New large loads must provide financial security to protect against stranded costs.
Took effect 1 July 2026
Indiana
Enacted
HB 1007: Energy generation resources.
Energy utilities must file expedited generation resource plans with the Indiana utility regulatory commission to acquire generation resources when load growth exceeds five percent of average peak demand or 150 megawatts. Energy utilities serving large load customers must petition the commission for project approval, with large load customers providing at least eighty percent reimbursement of project costs.
Took effect 1 July 2025
Kansas
Enacted
SB 92: Extending the expiration date for provisions that authorize an electric utility to not offer parallel generation service to certain large load customers and exempt certain large load customers from the determination of the utility's peak demand.
Every utility providing retail electric service must enter into parallel generation service contracts with customers in good standing who attach listed devices to export excess power from distributed energy systems, except utilities need not serve new or expanded large load customers at 34.5 kilovolts or higher commencing July 1, 2025. Utilities must approve or deny applications within 90 calendar days and compensate customers at least 100% of monthly avoided cost.
Maine
Enacted
LD 912: An Act To Address The Use Of Electricity By Data Centers
A generation service provider may not provide to data centers in the State a cumulative amount of electricity in a calendar year that exceeds 25% of the total electricity sold by that generation service provider to all of its customers in the State in that calendar year. Generation service providers must file quarterly reports with the commission identifying each data center served, electricity sold to each data center that quarter, and other information the commission requires.
Nebraska
Enacted
LB 1010: Adopt the Large Load Customer Regulation Act, provide for eminent domain relating to energy storage and regulation and taxation of energy storage resources, and change provisions relating to cryptocurrency mining operations and data centers
Public power suppliers must establish standards for interconnecting large load customers exceeding twenty megawatts, including disclosure requirements, study fees of fifty thousand dollars or one thousand dollars per megawatt (whichever is greater), and procedures for procuring demand response and requiring load curtailment during grid emergencies. Private electric suppliers must obtain board approval before constructing energy storage resources and demonstrate power purchase agreements with public entities.
Enacted
LB 526: Provide powers and duties for public power districts related to cryptocurrency mining operations
Public power suppliers may impose requirements on cryptocurrency mining operations of one megawatt or greater for infrastructure upgrade costs, including direct payment, letters of credit, or terms and conditions. Requirements must be fair, reasonable, and not unduly discriminatory, and must follow a load study. Cryptocurrency mining operations must notify their local public power supplier and comply with interconnection requirements.
New Jersey
Enacted
A 796: Requires electric public utilities to develop and apply special rules for certain data centers to protect non-data center customers from increased costs.**
Each electric public utility must file a petition with the Board of Public Utilities within 180 days after the board establishes standards to develop a rate class and tariff for large data center customers. The tariff must ensure other customers do not subsidize large data center customers, protect against stranded costs, and incentivize energy efficiency and clean generation procurement.
Enacted
A 5466: Requires BPU to study effects of data centers on electricity costs.*
The Board of Public Utilities must carry out a study within one year of the effective date on the effects of data center electricity usage on electricity costs in the State. The board must determine whether non-data center customers unreasonably subsidize data center costs, estimate residential rate impacts, and assess policy alternatives including special tariffs for data centers. The board must submit findings to the Governor and Legislature within 15 months.
Ohio
Enacted
SB 103: Allow alternative rate plans for certain natural gas companies
Natural gas companies with infrastructure development riders may file alternative rate plans to serve large load customers consuming over 1.2 million Mcf annually. Plans must protect non-participating customers from stranded costs and require monthly cost credits. Natural gas companies must file commercial agreements with large load customers and certify costs will not be recovered from other customers.
Oregon
Enacted
HB 3546: Relating to large energy use facilities; and declaring an emergency.
The Public Utility Commission must create a separate service classification for large energy use facilities using 20 megawatts or more primarily engaged in data center services, with tariff schedules allocating or directly assigning costs. Electric companies must enter into 10-year or longer contracts with such facilities specifying service dates, minimum payment obligations, and meeting commission-required conditions.
South Carolina
Enacted
H 3309: Electrical Utilities
Electrical utilities must file monitoring reports quarterly showing actual rate base components, expenses, revenues, and earned return on equity. The Public Service Commission must issue annual orders adjusting rates if utilities' earnings exceed or fall below established ranges. Utilities may not include investments in new generating facilities over 250 megawatts in rate base except through general rate proceedings.
South Dakota
Enacted
HB 1038: allow the Public Utilities Commission to assess actual costs to data centers that are customers of public utilities.
The Public Utilities Commission may assess a data center customer of a public utility the actual costs associated with processing a request for approval of a contract with deviations or other electric service agreement, where the data center has a peak demand of ten megawatts or greater. Moneys collected must be forwarded to the state treasurer for deposit in the South Dakota Public Utilities Commission gross receipts tax fund.
Took effect 1 July 2026
Enacted
SB 135: protect residents from increased utility costs and utility shortages caused by data centers and clarify authority to regulate data centers.
Providers of electricity must establish separate terms and conditions for data centers with peak demand of ten megawatts or greater, requiring data centers to reimburse all costs fairly attributed to service demand and consumption. Operators of data centers must notify local water providers of projected water consumption and submit semi-annual water usage reports to the Board of Water Management.
Took effect 1 July 2026
Tennessee
Enacted
HB 1847: Computers and Electronic Processing - As enacted, generally prohibits a municipality or electric utility to pay or absorb the cost of electrical infrastructure incurred to serve a data center; makes related changes. - Amends TCA Title 5; Title 6; Title 7; Title 13 and Title 65.
The owner or operator of a data center must pay the full cost of infrastructure needed to support the data center. An electric utility must ensure that costs of infrastructure and electric services to a data center are paid solely by the data center owner or operator and must not raise rates to residential or other commercial or industrial customers due to data center demand.
Takes effect 1 January 2027
Texas
Enacted
SB 6: Relating to the planning for, interconnection and operation of, and costs related to providing service for certain electrical loads and to the generation of electric power by a water supply or sewer service corporation.
Large load customers in ERCOT requesting new or expanded interconnection exceeding 75 megawatts must disclose whether they are pursuing substantially similar requests elsewhere that would materially change their interconnection request. Interconnecting utilities must pass through reasonable interconnection costs to large load customers. Large load customers must disclose on-site backup generating facilities capable of serving at least 50 percent of on-site demand.
Virginia
Enacted
HB 2644: Electric cooperative subsidiaries; customers exceeding 90 megawatts demand.
Electric cooperatives and their affiliates must separate regulated utility services from unregulated business activities, except that cooperatives may make unregulated sales of electric power to members served by dedicated or excess facilities within their certificated service territory that contract to serve a demand reasonably expected to exceed 90 megawatts.
Took effect 1 July 2025
Bills that moved most recently
The 25 open large-load tariffs and cost allocation bills with the latest action. The Data Centers and Energy Load Tracker follows all 177.
Texas HB 547: Relating to county noise study requirements and site construction approval for facilities operated by certain large load electric customers, authorizing a fee.
What it would do: Authorizes counties to require large load electric customers to conduct pre-construction and post-construction noise studies, obtain site construction approval, and implement mitigation measures to comply with specified maximum sound levels in unincorporated areas.
Introduced
Texas HB 730: Relating to the interconnection of large load customers and the recovery of costs of generation facilities serving large load customers by electric utilities operating outside of the ERCOT power region.
What it would do: Restricts electric utilities outside ERCOT from recovering costs of generation facilities built to serve large load customers (exceeding 75 megawatts) unless the Public Utility Commission finds net benefits to other customers and cost allocation follows cost-causation principles. Requires the commission to establish interconnection standards for large load customers.
Introduced
Texas SB 32: Relating to the issuance by the Public Utilities Commission of Texas of a permit for the construction of a large computational load site; providing an administrative penalty.
What it would do: Requires the Public Utilities Commission of Texas, in collaboration with the Texas Commission on Environmental Quality, to issue permits before construction of large computational load sites with at least 75 megawatts of electric power demand, and allows administrative penalties for violations.
Introduced
Texas SB 35: Relating to the sharing of information related to large load customers by the independent organization certified for the ERCOT power region with the Texas Water Development Board.
What it would do: Requires the ERCOT independent organization to share information about large load customers subject to certain standards with the Texas Water Development Board for water planning purposes, with such information kept confidential and exempt from public disclosure.
Introduced
Montana LC 508: Generally revise public utility laws related to large load retail customers
What it would do: Prohibits retail customers with average monthly demand of 5,000+ kilowatts from purchasing electricity from public utilities unless they demonstrate no adverse impact to other customers. Requires the Public Service Commission to establish separate rate classifications and tariffs ensuring large load customers pay all costs and cannot shift expenses to other customers.
Introduced
Pennsylvania HB 2888: An Act establishing reporting and information submission requirements for hyperscale computer data centers operating in this Commonwealth; providing for alternative compliance payments, for energy plans, for water plans, for regional benefits plans, for ratepayer protections, for community benefit plans and agreements, for municipal comments, for confidentiality, for records, for lists of tenants, for enforcement, for regulations and guidelines and for municipal zoning; imposing duties on the Department of Environmental Protection, the Department of Community and Economic Development and the Pennsylvania Public Utility Commission; and imposing penalties.
What it would do: Requires hyperscale computer data centers in Pennsylvania to submit energy, water, and sustainability plans to state departments; procure specified percentages of incremental clean firm energy or make alternative compliance payments; create jobs and community benefits; and file annual reports on water, electricity use, and plan compliance.
In committee
Virginia SB 850: Data centers, large; moratorium, approval requirements, utility independent classifications, report.
What it would do: Imposes a moratorium on large data center approvals until July 1, 2028, requires public hearings and community investment programs for large data centers, mandates prevailing wage for data center construction, establishes independent utility rate classifications for large data centers, and requires an environmental impact report on data center development.
In committee
Pennsylvania HB 1667: An Act amending the act of March 4, 1971 (P.L.6, No.2), known as the Tax Reform Code of 1971, providing for residential clean energy tax credit; repealing provisions relating to Pennsylvania Economic Development for a Growing Economy (PA EDGE) Tax Credits; providing for Pennsylvania Economic Development for a Growing Economy (PA EDGE) Tax Credits and for energy ratepayer protection; establishing the Energy Ratepayer Protection Fund; in manufacturing and investment tax credit, further providing for tax credit certificates and providing for limitations; and making a repeal.
What it would do: Amends Pennsylvania tax law to establish educational tax credits for scholarships and educational programs, create tax credits for milk processing facilities and new baseload generation projects, modify sales tax exclusions, and eliminate gross receipts tax on electric energy sales.
Passed chamber
Congress H.R. 10809: Make Data Centers Pay Act
What it would do: Amends the Federal Power Act to require that electric utilities recover the full incremental cost of serving data centers and high-density computing facilities with 20+ megawatts of load from those facilities alone, prohibiting cost allocation to other ratepayers.
In committee
Pennsylvania HB 2828: An Act providing for tariffs for large computational load customers and for emergency load control procedures during regional resource adequacy shortfalls; and imposing duties on the Pennsylvania Public Utility Commission.
What it would do: Requires electric distribution companies to file tariffs for large computational load customers (over 25 MW) with 15-year terms, cost recovery mechanisms, and exit fees, while prohibiting cost-shifting to other customers and mandating emergency curtailment procedures prioritizing these customers during resource adequacy shortfalls.
Passed committee
Congress H.R. 9340: Ratepayer Protection Act
What it would do: Amends the Public Utility Regulatory Policies Act of 1978 to require electric utilities to recover full incremental costs of generation, transmission, or distribution upgrades from large-load customers (non-residential consumers with peak demand of 100+ megawatts for data centers), and to require such customers provide financial assurances before upgrades are made.
Passed chamber
New Jersey A 4801: Establishes certain protections against demand by large-load addition customers in State.
What it would do: Requires load-serving entities to impose PJM curtailment obligations solely on large-load addition customers (50 MW or more) and pass through reliability backstop procurement costs to those customers. Requires large-load addition customers to provide financial security and submit detailed information to PJM.
Passed chamber
Pennsylvania SB 1469: An Act amending Title 66 (Public Utilities) of the Pennsylvania Consolidated Statutes, in rates and distribution systems, providing for large load hyperscale data center tariffs.
What it would do: Requires the Public Utilities Commission to promulgate regulations establishing a separate large load tariff rate class for hyperscale data centers (those with peak load of 25 megawatts or above individually or 50 megawatts in aggregate) that accounts for full costs of service without shifting costs to other ratepayers.
In committee
Pennsylvania SB 1473: An Act amending Title 66 (Public Utilities) of the Pennsylvania Consolidated Statutes, in restructuring of electric utility industry, further providing for definitions and for standards for restructuring of electric industry.
What it would do: Adds definitions for 'data center' and 'hyperscale data center' to Pennsylvania's public utilities law. Requires hyperscale data centers built after the effective date to provide their own baseload generation built in Pennsylvania and pay all interconnection costs with transmission and distribution systems.
In committee
Congress H.R. 10579: Energy Cost Fairness and Reliability Act of 2026
What it would do: Amends the Federal Power Act to require FERC to establish interconnection procedures for large load facilities (over 50 megawatts) seeking transmission system access, including requirements for demand flexibility, new generation resources, cost responsibility for studies and network upgrades, and labor standards for prioritized projects.
In committee
Congress H.R. 10467: Data Center Fairness Fee Act of 2026
What it would do: Amends the Clean Air Act to require the EPA to impose and collect a charge of $0.01 per kilowatt-hour on data centers and cryptocurrency mining facilities with over 50 megawatts of capacity, plus an additional $0.05 per kilogram of carbon dioxide equivalent for high-pollution facilities, beginning 2027.
In committee
Michigan SB 1047: Public utilities: rates; separate rate class for large-load customers; require. Amends 1939 PA 3 (MCL 460.1 - 460.11) by adding sec. 10ii.
What it would do: Requires covered utilities to submit tariffs or contracts for new or expanding data centers and large energy use facilities (20+ megawatts) to the commission or governing board for approval, with specified requirements including minimum 20-year contracts, collateral, demand response participation, clean energy procurement, and cost recovery mechanisms.
In committee
Congress H.R. 10322: Data Center Fair Share Act
What it would do: Amends the Public Utility Regulatory Policies Act of 1978 to require electric utilities to recover full incremental costs of generation, transmission, or distribution upgrades from large-load customers (100+ megawatts peak demand). Withholds 100 percent of highway apportionment funds from States that do not implement this standard.
In committee
Congress H.R. 10139: Ratepayer Bill of Rights Act of 2026
What it would do: Requires data centers with peak electricity demand of at least 50 megawatts or water withdrawal of at least 100,000 gallons per day to publicly disclose resource use, infrastructure costs, rate impacts, and public financial assistance, and prohibits ratepayers from subsidizing project-driven costs.
In committee
Virginia HB 1515: Local approval of data centers; temporary moratorium.
What it would do: Prohibits localities from granting final approval for rezoning, special exceptions, special use permits, site plans, or plans of development for new data centers until either all pending interconnection requests from data center customers to electric utilities are fulfilled or July 1, 2028, whichever is earlier.
In committee
Virginia HB 503: Electric utilities; cost recovery, costs substantially related to serving data center customers.
What it would do: Amends electric utility rate regulation to prohibit including costs substantially related to serving data center customers with peak demand of 100+ megawatts in general rates unless those costs are recovered solely from data center customers.
In committee
Virginia HB 591: Data centers; policy of the Commonwealth.
What it would do: Establishes as Commonwealth policy the encouragement of responsible data center operation while supporting grid reliability and renewable energy deployment, directing the Commonwealth to promote coordination between data centers and grid operators, incentivize demand response and energy storage, ensure equitable infrastructure cost contribution, require energy and water usage reporting, and promote cybersecurity measures.
Passed chamber
Virginia HB 906: Energy load flexibility protocols; SCC et al., to evaluate high electric demand customers, report.
What it would do: Directs the State Corporation Commission to convene a work group to evaluate electric load flexibility protocols for high electric demand customers and submit recommendations by November 1, 2026, considering grid reliability, fairness, and clean energy goals.
In committee
Virginia SB 339: SCC; cost allocation proceedings for certain electric utilities, definitions.
What it would do: Directs the State Corporation Commission to review whether Phase I and Phase II electric utilities' cost allocations require non-high-load customers to unreasonably subsidize high-load customers' transmission, generation, and distribution costs, with proceedings due by January 1, 2027 and 2028 respectively.
Passed chamber
Virginia SB 467: High load facilities; impact assessments.
What it would do: Requires local governing bodies to obtain a State Corporation Commission finding of no or minimal impact before approving land-disturbing permits for high load facilities exceeding 90 megawatts electricity demand. Directs the Commission to assess impacts on grid reliability, capacity constraints, and utility obligations within 120 days.
In committee
Large-load tariffs and cost allocation laws, state by state
- Virginia22 bills, 1 enacted
- New Jersey12 bills, 2 enacted
- New York11 bills
- Pennsylvania9 bills
- Congress9 bills
- California8 bills, 4 enacted
- Texas8 bills, 1 enacted
- South Carolina6 bills, 1 enacted
- Arizona5 bills, 1 enacted
- Idaho5 bills, 1 enacted
- North Carolina5 bills
- Ohio5 bills, 1 enacted
- South Dakota5 bills, 2 enacted
- Colorado4 bills
- Delaware4 bills, 4 enacted
- Iowa4 bills
- Indiana4 bills, 1 enacted
- Nebraska4 bills, 2 enacted
- Connecticut3 bills
- Maryland3 bills
- Michigan3 bills
- New Hampshire3 bills
- Tennessee3 bills, 1 enacted
- Alaska2 bills
- Florida2 bills, 1 enacted
- Georgia2 bills
- Hawaii2 bills
- Kentucky2 bills
- Massachusetts2 bills
- Montana2 bills
- Rhode Island2 bills
- Utah2 bills
- Washington2 bills
- Wyoming2 bills
- Alabama1 bill, 1 enacted
- Arkansas1 bill
- District of Columbia1 bill
- Kansas1 bill, 1 enacted
- Louisiana1 bill
- Maine1 bill, 1 enacted
- Missouri1 bill
- Oklahoma1 bill
- Oregon1 bill, 1 enacted
- Wisconsin1 bill
Questions
Which states have large-load tariffs and cost allocation laws?
States that enacted large-load tariffs and cost allocation laws in 2025 and 2026: California (4), Delaware (4), Nebraska (2), New Jersey (2), South Dakota (2), Alabama (1), Arizona (1), Florida (1), Idaho (1), Indiana (1), Kansas (1), Maine (1), Ohio (1), Oregon (1), South Carolina (1), Tennessee (1), Texas (1) and Virginia (1). Laws enacted before 2025 are not listed here.
Which states have the most large-load tariffs and cost allocation bills?
Virginia (22), New Jersey (12), New York (11), Pennsylvania (9) and Congress (9). In all, 177 bills in 44 jurisdictions, the latest action on 9 November 2026.
What do large-load tariffs and cost allocation bills cover?
Rates, contracts, minimum demand charges, collateral and exit fees for very large electric customers, and keeping their grid costs off other ratepayers. Each enacted law above has a line on what it requires.
Is this legal advice?
No. Which bills count as large-load tariffs and cost allocation bills, and the line on what each law requires or each bill would do, are drafted by software and not reviewed by an attorney. Every bill links to the legislature’s own record: read the text before relying on it. The list covers bills from the 2025 and 2026 sessions.
Follow large-load tariffs and cost allocation bills in every state
The Data Centers and Energy Load Tracker sends the bills that moved and a monthly report you can forward to a client.