Kentucky data center and energy laws

What Kentucky has enacted on data center and energy, what each law requires, and what the bills still moving would do. Kentucky is one of 29 states that enacted a data center and energy law in the 2025 and 2026 sessions.

5 new Kentucky laws take effect in 2027

Bills in scope
7bills in scope
Past committee
2past committee
Most recent action
31 March 2026most recent action

Data center and energy laws enacted in Kentucky

One data center and energy law enacted in the Kentucky Legislature in the 2025 and 2026 sessions, newest first. Each links to the legislature's own page.

  • HB 701AN ACT relating to blockchain digital assets.Enacted 24 March 2025

    What it requires: Individuals may accept digital assets for payment and use wallets without prohibition. Digital assets used as payment shall not face additional taxes or charges based solely on that use. Local governments cannot change zoning for digital asset mining businesses to discriminate against them without notice and comment process.

    Siting, zoning and permitting

Data center and energy in Kentucky, by topic

Data center and energy bills in Kentucky

The bills not yet law, furthest along first, with what each would do.

1Enacted

1Past committee

5Introduced or inactive

7 bills in scope

Past committee

1

HB 593AN ACT relating to data centers.Passed chamber

What it would do: Requires municipal electric utilities and retail electric suppliers to establish tariffs and contracts for data center customers with minimum application fees of $75,000, dedicated resources for facilities exceeding 25-250 megawatts, and full cost allocation ensuring no subsidization of data centers by other customers.

Introduced or inactive

5

HB 937AN ACT relating to high intensity technological infrastructure.In committee

What it would do: Establishes regulatory framework for high intensity technological infrastructure projects like data centers, requiring community impact reports, site review plans, community benefits agreements, and either conditional use permits or administrative review permits depending on location and local zoning authority.

HB 856AN ACT relating to data centers.In committee

What it would do: Requires data centers with peak energy demand of 15 megawatts or greater to obtain cabinet approval and submit a water feasibility study before commencing operations, and to submit annual water usage reports starting July 1, 2027.

SB 319AN ACT relating to data centers.In committee

What it would do: Requires data centers on former agricultural land with peak electric load over 50 megawatts to file decommissioning plans and post bonds ensuring restoration. Amends data center tax incentive agreements to require energy efficiency and water conservation practices.

SB 330AN ACT relating to data centers.In committee

What it would do: Prohibits public agencies from entering data center agreements that expand confidentiality beyond state law and voids provisions waiving Kentucky's Open Records and Open Meetings Acts. Requires disclosure of data center owner identity, location, public incentives, infrastructure needs, and environmental commitments.

HB 544AN ACT relating to data centers.In committee

What it would do: Requires retail electric suppliers to file commission-approved tariffs with minimum service requirements before serving data center customers with total aggregated contract capacity exceeding 100 megawatts, and mandates cost allocation ensuring data centers pay incremental costs without adversely impacting other customer classes.

Bill titles link to the Kentucky Legislature's own page.

What LawSignals covers

What counts as data center and energy legislation

In scope: Large-load tariffs and cost allocation; siting, zoning and permitting; tax incentives and clawbacks; on-site and co-located generation; water, cooling and emissions; and grid reliability and load flexibility.

Questions

Does Kentucky have a data center and energy law?

Yes. Kentucky enacted 1 data center and energy law in the 2025 and 2026 sessions, among them HB 701. Each is listed on this page with what it requires.

Which data center and energy bills are moving in Kentucky?

1 bill not yet law has passed a committee or a chamber, the furthest along HB 593 (passed chamber).

What does Kentucky legislate on most in data center and energy?

Siting, zoning and permitting (4 bills), Water, cooling and emissions (3 bills) and Large-load tariffs and cost allocation (2 bills).

Are these summaries reviewed by a lawyer?

No. Which bills count as Data center and energy bills, and the line on what each law requires or each bill would do, are drafted by software from the bill's own text and not reviewed by an attorney. Every bill links to the legislature's own record: read the text before relying on it. The list covers bills from the 2025 and 2026 sessions.

Know when Kentucky's data center and energy law changes

An alert when a bill moves, and one report a month on what changed in every state and Congress.