Virginia data center and energy laws

What Virginia has enacted on data center and energy, what each law requires, and what the bills still moving would do. Virginia is one of 29 states that enacted a data center and energy law in the 2025 and 2026 sessions.

13 new Virginia laws take effect in 2027

Bills in scope
76bills in scope
Past committee
20past committee
Most recent action
2 November 2026most recent action

Data center and energy laws enacted in Virginia

8 data center and energy laws enacted in the Virginia Legislature in the 2025 and 2026 sessions, newest first. Each links to the legislature's own page.

  • HB 153Data centers; site assessment, sound profile of the high energy use facility.Took effect 1 July 2026

    What it requires: Prior to approving a rezoning, special exception, or special use permit for a new high energy use facility requiring 100 megawatts or more of electrical power, a locality shall require the applicant to submit a site assessment examining the sound profile on residential units and schools within 500 feet. The locality may also require examination of effects on water, agricultural resources, parks, historic sites, and forestland. The electric utility must submit a form describing substations and transmission voltage.

    Siting, zoning and permitting, Water, cooling and emissions

  • HB 323Data centers; Department of Energy shall lead efforts to accelerate use of waste heat, report.Took effect 1 July 2026

    What it requires: The Department of Energy shall lead efforts to accelerate waste heat use from data centers by identifying beneficial use opportunities, facilitating communication between data centers and heat users, evaluating best practices, developing recommendations, and convening a work group. The Department shall submit a report to specified legislative committees no later than September 1, 2026.

    Water, cooling and emissions

  • SB 553Certain data from water users; water use consumption for domestic, etc., purposes, data centers.Takes effect 1 January 2027

    What it requires: Water users withdrawing surface or subsurface water must register annual water withdrawal and use data with the Board if withdrawal exceeds one million gallons in any single month for crop irrigation or daily average exceeds 10,000 gallons per day for other uses. Water users providing water offsite must report potable and reclaimed water volumes separately by category including data centers, domestic, and commercial/industrial purposes.

    Water, cooling and emissions

  • SB 94Data centers; site assessment, sound profile of the high energy use facility.Took effect 1 July 2026

    What it requires: Prior to approving a rezoning, special exception, or special use permit for a new high energy use facility requiring 100 megawatts or more of electrical power, a locality shall require the applicant to submit a site assessment examining the sound profile on residential units and schools within 500 feet. The locality may also require examination of effects on water, agricultural, park, historic, and forest resources. The electric utility must submit a form describing substations and transmission voltage.

    Siting, zoning and permitting, Water, cooling and emissions

  • HB 507Data centers; permit requirements, emission limits for certain engine-generator sets.Took effect 1 July 2026

    What it requires: The Department shall not issue a permit for a data center application submitted on or after July 1, 2026, unless the emission limit for each engine-generator set is equal to or less than the emissions achieved by a Tier 4 equivalent gen-set. The Department may establish more stringent emission limits.

    Water, cooling and emissions

  • HB 557Tangible personal property tax; establishes classification for electric landscaping equipment.Took effect 1 July 2026

    What it does: Adds electric-powered landscaping equipment employed in a trade or business to the list of tangible personal property classifications for local taxation, including battery-powered or electric outlet-powered lawn mowers, edgers, trimmers, leaf blowers, and chainsaws.

  • HB 1601Data centers; site assessment for high energy use facility.Enacted 2 May 2025

    What it does: This is a conference committee report on House Bill 1601 regarding data centers and site assessment for high energy use facilities. The report recommends rejecting the Senate Amendment and accepting an alternative Amendment in the Nature of a Substitute.

    Siting, zoning and permitting

  • HB 2644Electric cooperative subsidiaries; customers exceeding 90 megawatts demand.Took effect 1 July 2025

    What it requires: Electric cooperatives and their affiliates must separate regulated utility services from unregulated business activities, except that cooperatives may make unregulated sales of electric power to members served by dedicated or excess facilities within their certificated service territory that contract to serve a demand reasonably expected to exceed 90 megawatts.

    Large-load tariffs and cost allocation

Data center and energy in Virginia, by topic

Data center and energy bills in Virginia

The bills not yet law, furthest along first, with what each would do.

8Enacted

1Cleared both chambers

11Past committee

1Active in committee

55Introduced or inactive

76 bills in scope

Cleared both chambers

1

HB 285Distributed Energy Resources Task Force; created, membership, reports, sunset.Vetoed

What it would do: Creates a 15-member Distributed Energy Resources Task Force to develop strategies for energy affordability and distributed energy resource markets in compliance with FERC Order No. 2222, requiring reports by November 1, 2026, and expiring July 1, 2027.

Past committee

11

HB 1502Standby generators; DEQ shall conduct a study of generators used by by commercial facilities, etc.Passed chamber

What it would do: Requires the State Air Pollution Control Board to adopt regulations establishing emissions standards for standby generators at data centers, addressing nitrogen oxides and particulate matter. New generators must comply upon installation; existing generators have up to five years to comply through replacement, retrofit, or retirement.

HB 591Data centers; policy of the Commonwealth.Passed chamber

What it would do: Establishes as Commonwealth policy the encouragement of responsible data center operation while supporting grid reliability and renewable energy deployment, directing the Commonwealth to promote coordination between data centers and grid operators, incentivize demand response and energy storage, ensure equitable infrastructure cost contribution, require energy and water usage reporting, and promote cybersecurity measures.

SB 336Tier 2 emergency generators; SCC shall evaluate impact of requiring data centers to limit use, etc.Passed chamber

What it would do: Directs the State Corporation Commission to evaluate requiring data centers to limit Tier 2 generator use to sudden outages and prioritize Tier 4 equivalent or better generators, considering environmental impact, retrofit feasibility, and practices in other states and industries, with findings due by October 15, 2026.

SB 339SCC; cost allocation proceedings for certain electric utilities, definitions.Passed chamber

What it would do: Directs the State Corporation Commission to review whether Phase I and Phase II electric utilities' cost allocations require non-high-load customers to unreasonably subsidize high-load customers' transmission, generation, and distribution costs, with proceedings due by January 1, 2027 and 2028 respectively.

SB 417Cloud Computing Cluster Infrastructure Grant Fund; reclaimed water usage, definitions.Passed committee

What it would do: Amends the Cloud Computing Cluster Infrastructure Grant Fund statute to define reclaimed water and water-dependent cooling, and requires qualified companies operating facilities with water-dependent cooling to use reclaimed water for increasing percentages of cooling processes, reaching 100 percent by July 1, 2031.

SB 619Electric utilities; certificate of operation for high-load facilities.Passed chamber

What it would do: Requires any person operating a high-load facility with electricity demand exceeding 90 megawatts and not in operation before January 1, 2027 to obtain a certificate of operation from the State Corporation Commission, which must find no material adverse effects on utility rates, reliability, environmental compliance, and public interest.

HB 897Retail Sales and Use Tax; exemption for data centers, delayed effective date.Passed chamber

What it would do: Amends Virginia's retail sales and use tax exemption for data centers to require operators to use clean energy resources, non-carbon dioxide-emitting backup power, and implement environmental management systems beginning July 1, 2027, with compliance deadlines extending through 2035.

SB 130Data centers; site assessment, definition of high energy use facility.Passed committee

What it would do: Requires localities to mandate site assessments examining sound profiles near residential units and schools within 500 feet of new data centers requiring 100 megawatts or more of electrical power, and requires electric utilities to submit information about substations and transmission voltage needed to serve such facilities.

SB 960Electric utilities; data center cost allocation.Passed chamber

What it would do: Directs the State Corporation Commission to determine in at least one biennial review proceeding filed between January 1, 2025 and July 1, 2027 whether Phase I and Phase II utilities are using reasonable customer classifications in their rates, tolls, charges, or schedules.

SB 1353High-energy facilities; water and energy usage info. reports statewide clearinghouse established.Passed committee

What it would do: Requires owners or operators of high-energy facilities over 30 megawatts to submit quarterly reports on energy and water usage to the Department of Environmental Quality starting May 1, 2026, and establishes a publicly accessible statewide clearinghouse for this information by July 1, 2026.

HB 338Siting of data centers; locality may perform site assessment before approval.Passed chamber

Active in committee

1

SB 850Data centers, large; moratorium, approval requirements, utility independent classifications, report.In committee

What it would do: Imposes a moratorium on large data center approvals until July 1, 2028, requires public hearings and community investment programs for large data centers, mandates prevailing wage for data center construction, establishes independent utility rate classifications for large data centers, and requires an environmental impact report on data center development.

Introduced or inactive

12 of 55 shown

SB 843Data centers; state permitting, local approval, moratorium, sunset.In committee

What it would do: Prohibits localities from approving data center rezoning, permits, or site plans on or after July 1, 2027, and prohibits state agencies from approving data center permits or authorizing related electric distribution facilities. The moratorium expires July 1, 2030.

SB 841Data centers; public hearing and notice requirements.In committee

What it would do: Adds enhanced public notice and hearing requirements for data center zoning changes, requiring advertisements to include applicant name, anticipated owner/end user, utility infrastructure details, and mandating at least two public hearings for data center rezoning or zoning text amendments.

HB 1515Local approval of data centers; temporary moratorium.In committee

What it would do: Prohibits localities from granting final approval for rezoning, special exceptions, special use permits, site plans, or plans of development for new data centers until either all pending interconnection requests from data center customers to electric utilities are fulfilled or July 1, 2028, whichever is earlier.

HB 503Electric utilities; cost recovery, costs substantially related to serving data center customers.In committee

What it would do: Amends electric utility rate regulation to prohibit including costs substantially related to serving data center customers with peak demand of 100+ megawatts in general rates unless those costs are recovered solely from data center customers.

HB 607Aggregate air pollution; Department of Environmental Quality to study, data center generators.In committee

What it would do: Directs the Department of Environmental Quality to conduct a three-year study modeling aggregate air pollution scenarios in areas with large volumes of data centers and provide recommendations for handling minor air permits for data center generators and air quality monitoring needs, with findings due by October 1, 2029.

HB 641Virginia's Great Outdoors Act; established, creates data center land conservation tax.In committee

What it would do: Establishes Virginia's Great Outdoors Act and imposes a $3 per square foot data center land conservation tax on data center operators with facilities of 25,000 square feet or more, beginning January 1, 2027, with no less than $250 million in annual revenues distributed starting July 1, 2028 to various land conservation, recreation, and tribal programs.

HB 906Energy load flexibility protocols; SCC et al., to evaluate high electric demand customers, report.In committee

What it would do: Directs the State Corporation Commission to convene a work group to evaluate electric load flexibility protocols for high electric demand customers and submit recommendations by November 1, 2026, considering grid reliability, fairness, and clean energy goals.

SB 393Virginia's Great Outdoors Act; established, creates data center land conservation tax.In committee

What it would do: Establishes Virginia's Great Outdoors Act and creates a data center land conservation tax of $3 per square foot on data center operators, with no less than $250 million in annual revenues distributed to state parks, trails, land conservation, historic preservation, and tribal programs beginning July 1, 2028.

SB 466Electric utilities; cost recovery, costs substantially related to serving data center customers.In committee

What it would do: Amends Virginia's electric utility rate regulation to prohibit allocating costs of electric distribution infrastructure primarily serving data center loads to other customers, requiring such costs be recovered solely from the data center customer.

SB 467High load facilities; impact assessments.In committee

What it would do: Requires local governing bodies to obtain a State Corporation Commission finding of no or minimal impact before approving land-disturbing permits for high load facilities exceeding 90 megawatts electricity demand. Directs the Commission to assess impacts on grid reliability, capacity constraints, and utility obligations within 120 days.

SB 700Large-Scale Electricity Consumer Infrastructure Impact Fund; created.In committee

What it would do: Creates the Large-Scale Electricity Consumer Infrastructure Impact Fund and requires large-scale electricity consumers (over 25 megawatts demand) and localities approving such facilities after January 1, 2028, to pay annual infrastructure impact fees to the fund for offsetting utility infrastructure costs and providing residential bill credits.

SB 93Data centers; taxes on banks that are tenants of a center.In committee

What it would do: Beginning July 1, 2026, banks as tenants in data centers are excluded from the sales tax exemption for computer equipment in data centers. Banks' computer equipment used in data centers is assessed as regular tangible personal property for tax purposes.

Showing the 25 furthest along of 68. Subscribers see all of them, filtered and searchable. Bill titles link to the Virginia Legislature's own page.

What LawSignals covers

What counts as data center and energy legislation

In scope: Large-load tariffs and cost allocation; siting, zoning and permitting; tax incentives and clawbacks; on-site and co-located generation; water, cooling and emissions; and grid reliability and load flexibility.

Questions

Does Virginia have a data center and energy law?

Yes. Virginia enacted 8 data center and energy laws in the 2025 and 2026 sessions, among them HB 153, HB 323 and SB 553. Each is listed on this page with what it requires.

When do Virginia's data center and energy laws take effect?

HB 153 on 1 July 2026, HB 323 on 1 July 2026, SB 553 on 1 January 2027, SB 94 on 1 July 2026 and HB 507 on 1 July 2026. The others have no single date in their text.

Which data center and energy bills are moving in Virginia?

12 bills not yet law have passed a committee or a chamber, the furthest along HB 285 (vetoed), HB 1502 (passed chamber) and HB 591 (passed chamber).

What does Virginia legislate on most in data center and energy?

Siting, zoning and permitting (24 bills), Water, cooling and emissions (23 bills) and Large-load tariffs and cost allocation (22 bills).

Are these summaries reviewed by a lawyer?

No. Which bills count as Data center and energy bills, and the line on what each law requires or each bill would do, are drafted by software from the bill's own text and not reviewed by an attorney. Every bill links to the legislature's own record: read the text before relying on it. The list covers bills from the 2025 and 2026 sessions.

Know when Virginia's data center and energy law changes

An alert when a bill moves, and one report a month on what changed in every state and Congress.