California AB 1577
California AB 1577: Data centers: reporting
- Status
- Enacted
- Enacted
- Takes effect
- Last action
What it does
Requires data center owners to submit energy consumption and operational information to the state Energy Commission and to local agencies when applying for permits, with annual public reporting in anonymized form.
What it requires
Owners or operators of data centers must submit specified information to the State Energy Resources Conservation and Development Commission upon energization and annually thereafter, including energy consumption, power usage effectiveness, and fuel consumption. Owners or operators must also submit energy consumption and sound level estimates to local agencies when applying for discretionary permits.
Drafted by software from the bill text and not reviewed by an attorney. Check the official text before relying on it.
History
Chaptered by Secretary of State - Chapter 434, Statutes of 2026.
Approved by the Governor.
Enrolled and presented to the Governor at 4 p.m.
Senate amendments concurred in. To Engrossing and Enrolling. (Ayes 58. Noes 11.).
Senate amendments concurred in. To Engrossing and Enrolling. (Ayes 58. Noes 11. Page 6695.).
In Assembly. Concurrence in Senate amendments pending.
Read third time. Passed. Ordered to the Assembly. (Ayes 29. Noes 10.).
Read third time. Passed. Ordered to the Assembly. (Ayes 29. Noes 10. Page 5920.).
Read second time. Ordered to third reading.
Read third time and amended. Ordered to second reading.
Read second time. Ordered to third reading.
Read second time and amended. Ordered returned to second reading.
From committee: Amend, and do pass as amended. (Ayes 5. Noes 2.) (August 13).
In committee: Referred to APPR. suspense file.
Read second time and amended. Re-referred to Com. on APPR.
More California data centers and energy legislation
- AB 2469Data centers: water use disclosuresEnacted, from 1 January 2027
- AB 2619Water resources: data centersEnacted, from 1 January 2027
- SB 887California Environmental Quality Act: environmental leadership development projects: data centers: geothermal powerplant projectsEnacted, from 1 January 2027
- AB 1095Data centers: waste heat energyDead
- SB 732Emergency backup generators: critical facilities: exemptionsDead
- AB 93Water resources: data centersVetoed
- AB 222Data centers: power usage effectiveness: cost shiftsPassed chamber
- AB 2383Electricity: data centersEnacted, from 1 January 2027
Know the next California data centers and energy law while it is a bill