Requires applicants to submit site assessments examining sound effects and other environmental impacts on nearby residential areas and schools before localities approve rezoning or permits for new high-energy data centers.
What it requires
Prior to approving a rezoning, special exception, or special use permit for a new high energy use facility requiring 100 megawatts or more of electrical power, a locality shall require the applicant to submit a site assessment examining the sound profile on residential units and schools within 500 feet. The locality may also require examination of effects on water, agricultural, park, historic, and forest resources. The electric utility must submit a form describing substations and transmission voltage.
Drafted by software from the bill text and not reviewed by an attorney. Check the official text before relying on it.
History
Acts of Assembly Chapter text (CHAP0568)
Approved by Governor-Chapter 568 (effective 7/1/2026)
Governor's Action Deadline 11:59 p.m., April 13, 2026
Enrolled Bill communicated to Governor on March 31, 2026
Signed by Speaker
Signed by President
Bill text as passed Senate and House (SB94ER)
Enrolled
Conference report agreed to by Senate (29-Y 10-N 0-A)
Conference report agreed to by House (91-Y 4-N 0-A)
Conference Report released
House Conferees: Thomas, Convirs-Fowler, Wyatt
Conferees appointed by House
Senate Conferees: Roem, Srinivasan, Stanley
Conferees appointed by Senate
More Virginia data centers and energy legislation
- HB 153Data centers; site assessment, sound profile of the high energy use facilityEnacted, from 1 July 2026
- HB 323Data centers; Department of Energy shall lead efforts to accelerate use of waste heat, reportEnacted, from 1 July 2026
- SB 553Certain data from water users; water use consumption for domestic, etc., purposes, data centersEnacted, from 1 January 2027
- HB 507Data centers; permit requirements, emission limits for certain engine-generator setsEnacted, from 1 July 2026
- HB 1601Data centers; site assessment for high energy use facilityEnacted
- HB 1515Local approval of data centers; temporary moratoriumIn committee
- HB 607Aggregate air pollution; Department of Environmental Quality to study, data center generatorsIn committee
- SB 850Data centers, large; moratorium, approval requirements, utility independent classifications, reportIn committee
Know the next Virginia data centers and energy law while it is a bill
LawSignals tracks bills in every state and Congress, and sends a monthly report on what changed.